F&S will be conducting a TEMPERATURE CONTROL OUTAGE affecting North RAL on Friday, March 26th from 6:00AM to 10:00AM. This outage is needed to relocate a pneumatic line as part of the ongoing ESCO project renovations. During this outage, building occupants may notice a fluctuation in room temperatures. Further details about this outage are listed below:
Outage Request Number: 48314
Outage Time : 2021/03/26 06:00 until 2021/03/26 10:00
Outage Type : TEMP CONTROL COMPRESSOR
Building : 0116 - ROGER ADAMS LABORATORY
Building Sections affected : RAL North
Building Services affected : Pneumatic temperature controls
Building Occupants Effect : Fluctuation in space temperatures
Associated Project Manager. : F&S Amber Vega-Perfetti, Schneider Electric Scott B. Russell 314-852-2796
Comments : Pneumatic pipe is located in wall between RAL N 16A and COJ.
Shutoff Location : INSIDE
Reason : Relocating pneumatic line to run new duct work. This work is part of U16061 EPC Proj 005.
If you have any further questions or concerns, please do not hesitate to email the SCS Facilities and Safety team at scs-facilities@mx.uillinois.edu. This information will also be available for viewing on the SCS Building Outages/Important Notices blog: www.scsbuildingoutages.blogspot.com.
Safety/Environmental Compliance Specialist– School of Chemical Sciences
94 Roger Adams Lab
217-300-6618