Thursday, March 25, 2021

TEMPERATURE CONTROL OUTAGE - NORTH RAL - MARCH 26TH FROM 6:00AM TO 10:00AM

TO ALL IN NORTH RAL:

F&S will be conducting a TEMPERATURE CONTROL OUTAGE affecting North RAL on Friday, March 26th from 6:00AM to 10:00AM. This outage is needed to relocate a pneumatic line as part of the ongoing ESCO project renovations. During this outage, building occupants may notice a fluctuation in room temperatures. Further details about this outage are listed below:

Outage Request Number: 48314

Outage Time : 2021/03/26 06:00 until 2021/03/26 10:00

Outage Type : TEMP CONTROL COMPRESSOR

Building : 0116 - ROGER ADAMS LABORATORY

Building Sections affected : RAL North

Building Services affected : Pneumatic temperature controls

Building Occupants Effect : Fluctuation in space temperatures

Associated Project Manager. : F&S Amber Vega-Perfetti, Schneider Electric Scott B. Russell 314-852-2796

Comments : Pneumatic pipe is located in wall between RAL N 16A and COJ.

Shutoff Location : INSIDE

Reason : Relocating pneumatic line to run new duct work. This work is part of U16061 EPC Proj 005.

If you have any further questions or concerns, please do not hesitate to email the SCS Facilities and Safety team at scs-facilities@mx.uillinois.edu. This information will also be available for viewing on the SCS Building Outages/Important Notices blog: www.scsbuildingoutages.blogspot.com.

 

Shane Brownfield

Safety/Environmental Compliance Specialist– School of Chemical Sciences

94 Roger Adams Lab

217-300-6618

sbrownfi@illinois.edu

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.