TO ALL IN SOUTH RAL:

F&S will be conducting a SPRINKLER OUTAGE affecting the 2nd floor of South RAL (rooms 231-279) from Wednesday, March 3rd at 6:00AM through Friday, March 5th at 2:30PM. This outage is needed to temporarily move sprinkler pipe sections to install new VAV controls as part of the ESCO project. Further details about this outage are listed below:

Approved Outage Details:

Outage Request Number: 48261

Outage Time : 2021/03/03 06:00 until 2021/03/05 14:30

Outage Type : SPRINKLER SYSTEM

Building : 0116 - ROGER ADAMS LABORATORY

Building Sections affected : South 2nd Floor

Building Services affected : Fire Sprinklers

Building Occupants Effect : None

Associated Project Manager. : Schneider Electric Scott B. Russell 314.852.2796

Comments : null

Shutoff Location : INSIDE

Reason : Multiple sprinkler pipe sections need to be temporarily moved in order to install new VAV controls. This work is part of U16061 EPC Proj 005.

If you have any further questions or concerns, please do not hesitate to email the SCS Facilities and Safety team at scs-facilities@mx.uillinois.edu. This information will also be available for viewing on the SCS Building Outages/Important Notices blog: www.scsbuildingoutages.blogspot.com.

 

Shane Brownfield

Safety/Environmental Compliance Specialist– School of Chemical Sciences

94 Roger Adams Lab

217-300-6618

sbrownfi@illinois.edu

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.