SPRINKLER OUTAGE - DAVENPORT HALL - OCTOBER 9TH THROUGH 16TH FROM 7:30 TO 3:30PM EACH WEEKDAY

TO ALL IN DAVENPORT:

F&S is conducting a SPRINKLER OUTAGE affecting Davenport Hall from October 9th through October 16th from 7:30AM to 3:30PM daily (on weekdays only). This outage is needed to install new sprinkler branch lines. Building occupants shouldn’t experience any effects from this outage. Further details of the outage are listed below:

Outage Request Number: 40914

Outage Time : 2020/10/09 07:30 until 2020/10/16 15:30

Outage Type : SPRINKLER SYSTEM

Building : 0001 - DAVENPORT HALL

Building Sections affected : Entire Building

Building Services affected : Fire Sprinkler System

Building Occupants Effect : Occupants shouldn't notice any effect from draining the fire sprinkler system.

Associated Project Manager. : F&S PM: Stan Lamaster 244-7844 Brent Moore, Broeren Russo Builders, Inc, 217-493-8027 Daniel Lenzini, MATCO Fire Protection, Inc., 217-493-3811

Comments : Weekdays only - DAILY outage.

Reason : Install new sprinkler branch lines for remodel project.

If you have any further questions or concerns, please do not hesitate to email the SCS Facilities and Safety team at scs-facilities@mx.uillinois.edu. This information will also be available for viewing on the SCS Building Outages/Important Notices blog: www.scsbuildingoutages.blogspot.com.

 

Shane Brownfield

Safety/Environmental Compliance Specialist– School of Chemical Sciences