Friday, May 4, 2018

VENTILATION OUTAGE - CLSL-A - MONDAY, MAY 7- 6:00AM TO 10:00AM

TO ALL IN CLSL-A:

F & S will be conducting a VENTILATION OUTAGE on MONDAY, MAY 7 from 6:00AM to 10:00AM.  The following spaces will be affected:  A151,A128,A133,AC130,A131G,A131,AC118,A245C,A228,A231,A233AC230,AC334,A333,A332,A331,A428,A430,A432,A434,A440,A442,A443,A443A,A443B,A446,A448,B401,A533,A534,A535,A535A,A540,A542,AC541,A544,A548,A550,A552,A554,B501,B503.
All occupants have already been notified.  This means there will be NO SUPPLY AIR TO ROOMS OR MAKE UP AIR FOR ANY FUME HOODS IN THOSE AREAS.  This outage is being done to clean the chilled water coils on the air handling unit that serves those areas.  Further information regarding the outage are below:

Approved Outage Details:
Outage Request Number: 5507
Outage Time : 2018/05/07 06:00 until 2018/05/07 10:00
Outage Type : VENTILATION
Building : 0070 - CHEMICAL & LIFE SCIENCES LABORATORY
Building Sections affected : A151,A128,A133,AC130,A131G,A131,AC118,A245C,A228,A231,A233AC230,AC334,A333,A332,A331,A428,A430,A432,A434,A440,A442,A443,A443A,A443B,A446,A448,B401,A533,A534,A535,A535A,A540,A542,AC541,A544,A548,A550,A552,A554,B501,B503.
Building Services affected : Make up air
Building Occupants Effect : There will be no supply air to rooms or make up air for any Fume Hoods in these areas.
Ventilation Fan No. : AHU-4
Ventilation Area. : see below
Reason : We need to clean the chilled water coils.

If you have any questions or concerns, please let us know.  You can also reference this information on the SCS Building Outages/Important Notices blog:  www.scsbuildingoutages.blogspot.com.

Thanks,

Ken Wooldridge
Operations Manager
School of Chemical Sciences
505 S Mathews
Urbana, IL 61801
PH 217 300-3347

Cell 217 202-4908