Monday, November 29, 2021

VENTILATION OUTAGE - CLSL-A - NOVEMBER 30TH FROM 7:00AM TO 3:00PM

TO ALL IN CLSL-A:

F&S will be conducting a VENTILATION OUTAGE affecting the designated areas of CLSL-A on Tuesday, November 30th from 7:00AM to 3:00PM. This outage is needed to install controls as part of the ongoing ESCO project renovations. During this outage, there will be no supply air available to those areas served by the S2 supply fan. These areas are highlighted in gray on the attached maps. Occupants in the affected areas may notice warmer than usual space temperatures. Further details about this outage are listed below:

Outage Request Number: 56994

Outage Time : 2021/11/30 07:00 until 2021/11/30 15:00

Outage Type : VENTILATION

Building : 0070 - CHEMICAL & LIFE SCIENCES LABORATORY

Building Sections affected : Floors 1, 2, 3, 4, & 5. (maps avail upon req to whitson@illinois.edu)

Building Services affected : AHU-S2

Building Occupants Effect : AHU-S2 will be shutdown for 8 hrs

Ventilation Fan No. : AHU-S2

Ventilation Area. : Floors 1, 2, 3, 4, & 5. (maps avail upon req to whitson@illinois.edu)

Comments : null

Shutoff Location : NOT APPLICABLE

Reason : Controls installations

If you have any further questions or concerns, please do not hesitate to email the SCS Facilities and Safety team at scs-facilities@mx.uillinois.edu. This information will also be available for viewing on the SCS Building Outages/Important Notices blog: www.scsbuildingoutages.blogspot.com.

 

Shane Brownfield, CCHO

Safety/Environmental Compliance Specialist– School of Chemical Sciences

94 Roger Adams Lab

217-300-6618

sbrownfi@illinois.edu